Sep 21, 2021 Step by Step Guide to Prepare for CSCP Exam BrainDumps
Supply Chain Professional CSCP Real Exam Questions and Answers FREE Updated on 2021
NEW QUESTION 190
Which of the following planning systems would the demand forecast typically be fed into first?
- A. MRP
- B. business plan
- C. MPS
- D. DRP
- E. CRP
Answer: D
NEW QUESTION 191
Companies are beginning to define customers by actual buying behaviors. This has led tosegmentation of customers into all of the following strategies EXCEPT:
- A. customer technical expertise
- B. customer awareness
- C. customer needs
- D. customer value to the business
Answer: B
NEW QUESTION 192
The use of standardized components typically results in:
- A. more items, larger bills of material (BOMS), and increased material requirements planning (MRP) run time.
- B. fewer inventory items and inventory levels.
- C. increased planning and control efforts to avoid shortages.
- D. smaller bills of materials, fewer routings, and fewer manufacturing orders.
Answer: D
NEW QUESTION 193
A firm has identified key benefits for developing a strategic alliance and has selected appropriate supply chain partners. Which of the following actions should the firm take to build a successful alliance with a supplier who is also a competitor?
- A. Negotiate contracts that maximize the firm's profits.
- B. Analyze market for competitive advantage.
- C. Establish processes to control shared information.
- D. Instruct employees to ignore the competitive aspect of the relationship.
Answer: B
NEW QUESTION 194
All of the following are modules of a transportation management system EXCEPT:
- A. yard management
- B. shipment tracking
- C. vehicle routing
- D. carrier management
- E. delivery scheduling
Answer: A
NEW QUESTION 195
CRM loyalty programs are designed with all of the following considerations in mind
EXCEPT:
- A. desired customer behavior
- B. positioning -- implications of loyalty programs
- C. cost and benefit structure of program elements
- D. service requirements of offering
Answer: D
NEW QUESTION 196
A firm has determined its cash-to-cash cycle time to be 60 days. The number of days' payables outstanding is 25, and number of days' sales outstanding is 35. If the firm reduces its inventory by 20%, the new cash-to-cash cycle time, in days, will be approximately:
- A. 88.
- B. 50.
- C. 48.
- D. 60.
Answer: B
NEW QUESTION 197
A key challenge in managing the supply chain for an innovative product is that:
- A. the product life cycle will be long.
- B. inventory levels must be minimal.
- C. contribution margins will be slim.
- D. product demand will be volatile.
Answer: D
NEW QUESTION 198
A company exports products to emerging markets. Which of the following approaches would be used to enhance compliance, minimize risks, and connect supply chain activities?
- A. Supply chain event management
- B. Logistics network planning
- C. Distribution requirements planning
- D. Global trade management
Answer: D
Explanation:
Section: Implementation and Operations
NEW QUESTION 199
A benefit of using radio frequency identification (RFID) instead of bar coding would be:
- A. lower cost
- B. the ability to read multiple items
- C. the ability to locate an individual item in a warehouse
- D. decreased cycle count requirements
Answer: B
NEW QUESTION 200
What is the most common type of database?
- A. object-oriented databases
- B. hierarchical databases
- C. network databases
- D. relational databases
Answer: D
Explanation:
Managing the Supply Chain: The Definitive Guide for the Business professional
NEW QUESTION 201
What impact does lumping have on the demand signal in terms of timing?
- A. it minimizes the need for signals
- B. it delays the timing
- C. it has no effect on the timing
- D. it speeds up the timing
Answer: B
NEW QUESTION 202
Supplier certification procedures verify that a supplier:
- A. is ISO certified.
- B. implements, documents, and improves procedures related to customer requirements.
- C. tracks manufacturing processes, including bills of material and routings to support the processes.
- D. manufactures products to the specifications shown on engineering documents and bills of material.
Answer: B
NEW QUESTION 203
Which of the following is a good example of a completely disconnected supply networks?
- A. Airbus vs. Boeing
- B. Compaq vs. HP
- C. PC vs. Mac
- D. Perdue Farms vs. Tyson Foods
Answer: D
NEW QUESTION 204
All of the following are predictable obstacles to building a successful collaborative supplychain EXCEPT:
- A. technology barriers
- B. bottlenecks caused by weaker partners
- C. trust-based relationships
- D. conflicting individual incentives and organizational goals
- E. suboptimization
Answer: C
NEW QUESTION 205
......
Ultimate Guide to Prepare CSCP Certification Exam for Supply Chain Professional: https://www.prepawayete.com/APICS/CSCP-practice-exam-dumps.html
CSCP Ultimate Study Guide: https://drive.google.com/open?id=1tsS3yXxAg4dCWVemeQcrfMqsAaFG65xn