PMI CAPM Exam Prep Guide Prep guide for the CAPM Exam [Q460-Q475]

Share

PMI CAPM Exam Prep Guide: Prep guide for the CAPM Exam

2022 New Preparation Guide of PMI CAPM Exam

NEW QUESTION 460
Which type of project life cycle uses an iteration plan?

  • A. Predictive
  • B. Product
  • C. Agile
  • D. Waterfall

Answer: D

 

NEW QUESTION 461
Another name for an Ishikawa diagram is:

  • A. control chart.
  • B. flowchart.
  • C. histogram.
  • D. cause and effect diagram.

Answer: D

Explanation:
Section: Volume D

 

NEW QUESTION 462
The document that guides project execution, monitoring and control, and closure is called:

  • A. The execution plan
  • B. The integration plan
  • C. The project management plan
  • D. The project charter

Answer: C

 

NEW QUESTION 463
For the given information:

Activity A, duration 5 days, predecessors: none
Activity B, duration 3 days, predecessors: none
Activity C, duration 6 days, predecessors: A and B
Activity D, duration 7 days, predecessors: B
Activity E, duration 4 days, predecessors: C and D
Activity F, duration 2 days, predecessors: E and B
Which of the following shows the project's critical path?

  • A. Start, B, D, E, F, Finish
  • B. Start, B, F, Finish
  • C. Start, A, C, E, F, Finish
  • D. Start, B, C, E, F, Finish

Answer: D

Explanation:
Section: Volume E

 

NEW QUESTION 464
Which Develop Schedule tool and technique produces a theoretical early start date and late start date?

  • A. Schedule compression
  • B. Critical path method
  • C. Schedule comparison bar charts
  • D. Variance analysis

Answer: B

Explanation:
Section: Volume C
Explanation:
6.6.2.2 Critical Path Method
The critical path method, which is a method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model. This schedule network analysis technique calculates the early start, early finish, late start, and late finish dates for all activities without regard for any resource limitations by performing a forward and backward pass analysis through the schedule network, as shown in Figure 6-18. In this example the longest path includes activities A, C, and D, and, therefore, the sequence of A-C-D is the critical path. The critical path is the sequence of activities that represents the longest path through a project, which determines the shortest possible project duration. The resulting early and late start and finish dates are not necessarily the project schedule, rather they indicate the time periods within which the activity could be executed, using the parameters entered in the schedule model for activity durations, logical relationships, leads, lags, and other known constraints. The critical path method is used to calculate the amount of scheduling flexibility on the logical network paths within the schedule model.
On any network path, the schedule flexibility is measured by the amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint, and is termed "total float." A CPM critical path is normally characterized by zero total float on the critical path. As implemented with PDM sequencing, critical paths may have positive, zero, or negative total float depending on constraints applied. Any activity on the critical path is called a critical path activity. Positive total float is caused when the backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during forward pass calculation. Negative total float is caused when a constraint on the late dates is violated by duration and logic. Schedule networks may have multiple near-critical paths.
Process: 6.6 Develop Schedule
Definition: The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model.
Key Benefit: The key benefit of this process is that by entering schedule activities, durations, resources, resource availabilities, and logical relationships into the scheduling tool, it generates a schedule model with planned dates for completing project activities.
Inputs
1. Schedule management plan
2. Activity list
3. Activity attributes
4. Project schedule network diagrams
5. Activity resource requirements
6. Resource calendars
7. Activity duration estimates
8. Project scope statement
9. Risk register
10.Project staff assignments
11.Resource breakdown structure
12.Enterprise environmental factors
13.Organizational process assets
Tools & Techniques
1. Schedule network analysis
2. Critical path method
3. Critical chain method
4. Resource optimization techniques
5. Modeling techniques
6. Leads and lags
7. Schedule compression
8. .Scheduling tool
Outputs
1. Schedule baseline
2. .Project schedule
3. Schedule data
4. Project calendars
5. Project management plan updates
6. Project documents updates

 

NEW QUESTION 465
A project manager can choose from several techniques to resolve conflicts between team members. Which technique can result in a win-win situation?

  • A. Collaborate/Problem Solve
  • B. Compromise/Reconcile
  • C. Smooth/Accommodate
  • D. Withdraw/Avoid

Answer: A

Explanation:
Section: Volume E
Explanation/Reference: https://4squareviews.com/2013/06/26/5th-edition-pmbok-guide-chapter-9-conflict-resolution/

 

NEW QUESTION 466
Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?

  • A. Direct and Manage Project Work
  • B. Monitor and Control Project Work
  • C. Plan Quality Management
  • D. Develop Project Management Plan

Answer: D

Explanation:
Section: Volume A
Explanation:
Process: 4.2. Develop Project Management Plan
Definition: The process of defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive project management plan. The project's integrated baselines and subsidiary plans may be included within the project management plan.
Key Benefit: The key benefit of this process is a central document that defines the basis of all project work.
Inputs
1. Project charter
2. Outputs from other processes
3. Enterprise environmental factors
4. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Facilitation techniques
Outputs
1. Project management plan
4.2.3.1 Project Management Plan
The project management plan is the document that describes how the project will be executed, monitored, and controlled. It integrates and consolidates all of the subsidiary plans and baselines from the planning processes.
Project baselines include, but are not limited to:
Scope baseline (Section 5.4.3.1),

Schedule baseline (Section 6.6.3.1), and

Cost baseline (Section 7.3.3.1).

Subsidiary plans include, but are not limited to:
Scope management plan (Section 5.1.3.1),

Requirements management plan (Section 5.1.3.2),

Schedule management plan (Section 6.1.3.1),

Cost management plan (Section 7.1.3.1),

Quality management plan (Section 8.1.3.1),

Process improvement plan (Section 8.1.3.2),

Human resource management plan (Section 9.1.3.1),

Communications management plan (Section 10.1.3.1),

Risk management plan (Section 11.1.3.1),

Procurement management plan (Section 12.1.3.1), and

Stakeholder management plan (Section 13.2.3.1).

Among other things, the project management plan may also include the following:
Life cycle selected for the project and the processes that will be applied to each phase;

Details of the tailoring decisions specified by the project management team as follows:

○ Project management processes selected by the project management team,
○ Level of implementation for each selected process,
○ Descriptions of the tools and techniques to be used for accomplishing those processes, and
○ Description of how the selected processes will be used to manage the specific project, including the dependencies and interactions among those processes and the essential inputs and outputs.
Description of how work will be executed to accomplish the project objectives;

Change management plan that documents how changes will be monitored and controlled;

Configuration management plan that documents how Configuration management will be performed;

Description of how the integrity of the project baselines will be maintained;

Requirements and techniques for communication among stakeholders; and

Key management reviews for content, the extent of, and timing to address, open issues and pending

decisions.
The project management plan may be either summary level or detailed, and may be composed of one or more subsidiary plans. Each of the subsidiary plans is detailed to the extent required by the specific project. Once the project management plan is baselined, it may only be changed when a change request is generated and approved through the Perform Integrated Change Control process.

 

NEW QUESTION 467
A project manager is analyzing a few network diagrams in order to determine the minimum duration of a project. Which diagram should the project manager reference?

  • A. A diagram in which the critical path method has been applied
  • B. A diagram in which resource optimization has been applied
  • C. A diagram in which a predefined series of activities has been organized
  • D. A diagram which shows a combination of resource and time optimization

Answer: A

Explanation:
Section: Volume E
Explanation/Reference: https://www.mindtools.com/pages/article/critical-path-analysis.htm

 

NEW QUESTION 468
Which of the following is an example of an organizational system that is arranged based on the job being performed?

  • A. Project-oriented
  • B. Simple
  • C. Multi-divisional
  • D. Functional

Answer: D

 

NEW QUESTION 469
The project manager released a report. A few stakeholders express the view that the report should not have been directed to them.
Which of the 5Cs of written communications does the project manager need to address?

  • A. Correct grammar and spelling
  • B. Coherent logical flow of ideas
  • C. Concise expression and elimination of excess words
  • D. Clear purpose and expression directed to the needs of the reader

Answer: D

 

NEW QUESTION 470
Work performance information and cost forecasts are outputs of which Project Cost Management process?

  • A. Control Costs
  • B. Determine Budget
  • C. Estimate Costs
  • D. Plan Cost Management

Answer: A

 

NEW QUESTION 471
Resource calendars are included in the:

  • A. work breakdown structure (WBS).
  • B. project charter.
  • C. staffing management plan.
  • D. project communications plan.

Answer: C

Explanation:
Section: Volume E

 

NEW QUESTION 472
Cost variance (CV) is equal to earned value:

  • A. Divided by planned value [EV/PV].
  • B. Minus actual cost [EV - AC].
  • C. Divided by actual cost [EV/AC].
  • D. Minus planned value [EV - PV].

Answer: B

Explanation:
Explanation/Reference:
Explanation:
CV = EV - AC
CPI = EV / AC
SV = EV - PV
SPI = EV / PV

 

NEW QUESTION 473
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?

  • A. Stakeholder register
  • B. Procurement documents
  • C. Project charter
  • D. Communications plan

Answer: C

 

NEW QUESTION 474
What is an example of an emerging trend in procurement management?

  • A. Online procurement tools provide buyers with multiple sources to advertise to sellers.
  • B. Online technologies allow a project's progress to be viewed by all stakeholders to build better relations.
  • C. Online procurement tools provide sellers with designated sources for procurement documents and the resources to complete them.
  • D. Online technologies enable projects to postpone ordering long lead items until the items are needed.

Answer: C

Explanation:
Section: Volume E

 

NEW QUESTION 475
......

Latest Questions CAPM Guide to Prepare Free Practice Tests: https://www.prepawayete.com/PMI/CAPM-practice-exam-dumps.html

CAPM Practice Exam - 1090 Unique Questions: https://drive.google.com/open?id=1BA9LW1oO1my0LSvB7PlqBsYC3Hc5DyB2

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 )
From Monday to Saturday

Support: Contact now