NEW QUESTION 15
While producing the Team Plan to deliver the agreed Work Package, it became apparent that the user representatives assigned 10 check some of the products were unsuitable.
Which 2 actions should the Team Manager take in response to this situation?

  • A. Notify the Project Manager by raising an Exception Report explaining that the original reviewers are unsuitable.
  • B. Consult the Senior Supplier to assign suitable reviewers.
  • C. Ensure the Quality Register is updated with details of the agreed amendments to the reviewers.
  • D. Discuss the situation with Project Assurance and agree the changes or additions to the reviewers. Advise the Project Manager of this risk.

Answer: B,D

 

NEW QUESTION 16
HOTSPOT
Column 1 is a list of entries from the Daily Log that occurred during stage 4 in the Controlling a Stage process. For each entry in Column 1, select the first management product from Column 2 that should have been updated, or created, as a result of the entry. Each selection from Column 2 can be used once, more than once or not at all.
Drop down the right answer from column 1 to column 2.
Hot Area:

Answer:

Explanation:

 

NEW QUESTION 17
The project is in stage 2. The project manager is reviewing stage status and has collected the checkpoint reports from the team managers. These show that the products are being completed on schedule.
However, project support has raised issues that quality reviews have not been completed as agreed. The project manager reports in the highlight report that the stage is progressing well.
Is this appropriate, and why?

  • A. No, because the issues raised by project support are a cause for concern and should be reflected in the highlight report.
  • B. Yes, because the highlight report is used to provide the project board with stage and project progress.
  • C. No, because the project manager should have recorded the cause of the delay to the quality reviews in the lessons log.
  • D. Yes, because the highlight report is a summary of the information in the checkpoint reports.

Answer: A

 

NEW QUESTION 18
Scenario
Additional Information
During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes:
There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff have not been recruited due to the reduced operation. If the project is successful, a recruitment campaign will be required to fill the existing staff vacancies and there may be a requirement for additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult to find.
In financial terms, there were a total of 1,500 orders in the last financial year, each with an average profit of
£2k. The Marketing department believes that sending a promotional calendar to our current and prospective customers would increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months from the date of distribution.
The Marketing Director will be funding the project from the business marketing budget. She believes that the effect of a good company image portrayed by a successful calendar would last into a second year. She has forecast the same increase in orders for a second year and predicts that the annual employee satisfaction survey will show a measurable improvement in staff morale.
A number of alternatives were explored, including:
* 20% discount for all repeat customers - not cost-effective and very short term
* A promotional calendar as a free Christmas gift - would target current and prospective customers and the benefits would last into a second year
* A series of television and press advertisements was too expensive
* A direct mail shot to all customers - benefit would be short term
* Creation of an internet website - would not suit all customers
The calendar is seen as the favored option, as long as the company's competitors do not increase their marketing activity. Whilst the Marketing department wants a very high quality, glossy product, the project management team must be aware of the cost this will incur.
Using the Project Scenario and the additional Information provided for this question In the Scenario Booklet, answer the following question.
Which 2 statements should be recorded under the Business options heading?

  • A. Produce a promotional calendar as a free Christmas gift to current and prospective customers.
  • B. Outsource the creation of the calendar to a professional marketing company.
  • C. Do nothing.
  • D. Create the photographs for the calendar internally.
  • E. Use a professional photographer to create the photographs for the calendar.

Answer: A,C

 

NEW QUESTION 19
Which of the following is not part of the composition of a Plan?

  • A. Product descriptions
  • B. Pre-requites
  • C. Assumptions
  • D. Quality responsibilities

Answer: D

 

NEW QUESTION 20
Which 2 statements correctly define a Business Case risk which should be recorded under the Major risks heading?

  • A. Staff morale will improve as a result of the promotional calendar.
  • B. Operational costs will increase as a result of the recruitment campaign.
  • C. If the calendar quality is poor customers will not use it, creating the reverse effect and reducing orders further.
  • D. The prepared calendar pack is to be delivered to the printers by the first week in December.
  • E. If any competitors launch a calendar at the same time this will reduce the impact of the MNO calendar and benefits will be reduced.

Answer: C,E

Explanation:
Explanation/Reference:
Testlet 2
Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers' performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:
● Do nothing.
● Re-engineer selected business functions.
● Outsource selected business functions.
The feasibility study concluded that there was a case for outsourcing the MFH Information Technology Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:
● One service provider should be contracted to provide the services currently provided by the Information Technology Division and the Facilities Division.
● A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes, systems and operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project:
● Use PRINCE2.
● Set up the project with 4 management stages:
Stage 1. Standard PRINCE2 initiation activities.
Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run trial period.
Initial estimates indicated that the project would cost £2.5m and take two years to complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of £20m over 10 years.
The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage.
Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.

 

NEW QUESTION 21
Scenario
Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required.
Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the business, particularly as this is a marketing project. She has the authority to commit the annual business marketing budget, from which the project will be funded, as she sees appropriate. She will be responsible for monitoring the expected benefits of the calendar, in particular the improvement of the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the company and is still as keen and energetic as the day he started. VVhilst he will not be part of the project team, his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document control. They now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and office equipment needs of the company and will supply the stationery for this project.
Portraits ltd: This is a professional photographic company with a number of excellent photographers and a history of successful work. This company has been selected to take the photos for the company calendar.
It has yet be decided which of the photographers to use.
Which 2 statements explain why the Marketing Director should be appointed as a Senior User for this project?

  • A. She previously had a successful career in publicity.
  • B. She can represent the Marketing department.
  • C. The project will be funded from the business marketing budget.
  • D. The Marketing department will help to deliver the benefits of this project.
  • E. A number of the products will be produced by the Sales department and the Marketing department.

Answer: B,D

 

NEW QUESTION 22
Which statement is an appropriate entry for the Initiation Stage Plan?

  • A. The plan is based on the external outsourcing consultants being available at the start of the initiation stage.
  • B. The initial project cost estimate of £2.5m, will have a tolerance of +£125k J*£75k.
  • C. The Daily Log has been updated with the new risks which were identified while preparing the Initiation Stage Plan.
  • D. The project management team will consist of representatives from the IT and Facilities Divisions.

Answer: A

 

NEW QUESTION 23
ABC Company carried out a similar project two years ago, in response to changes in health and safety legislation for the health service. The experiences from that project were used to refine the corporate risk management policy. For that reason, the project board decided to use the corporate risk management policy in the risk management approach for this project.
Is this appropriate, and why?

  • A. Yes, because experience from previous projects should be taken into account in the risk management approach.
  • B. Yes, because the corporate risk management policy was updated, as a result of lessons from previous projects.
  • C. No, because a separate risk management approach is not necessary when the company has a risk management policy.
  • D. No, because the risk management approach should be tailored to suit the project and its environment.

Answer: A

 

NEW QUESTION 24
It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.
There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.
Which product should register that the risk of a competitor producing a calendar at the same time was identified at the beginning of the project but the assessment of this risk appears to have been poor?

  • A. Follow-on action recommendations
  • B. Issue Register
  • C. Lessons Report
  • D. Risk Register

Answer: C

 

NEW QUESTION 25
Scenario
Additional Information
Product Description

Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors) Introduction
1. This document defines the approach to be taken to achieve the required quality levels during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Although it is not specified in the current corporate branding standards, the MFH corporate logo should be shown on the front page of the service level agreement.

  • A. Obtain agreement from the Director of Facilities Division to amend this within the remaining +2 days tolerance.
  • B. Raise an issue (request for change).
  • C. Raise an issue (off-specification).
  • D. Accept this error as a concession.

Answer: B

 

NEW QUESTION 26
Who is responsible for the initial creation of the Configuration Item records?

  • A. Project Assurance
  • B. Project Support
  • C. Project Manager
  • D. Team Manager

Answer: B

 

NEW QUESTION 27
Scenario
Additional Information
Product Description

Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors) Introduction
1. This document defines the approach to be taken to achieve the required quality levels during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
The service level agreement contains a number of technical terms that are missing from its glossary of terms.

  • A. Raise an issue (request for change).
  • B. Obtain agreement from the Director of Facilities Division to add these into the glossary of terms within the remaining +2 days' tolerance.
  • C. Raise an issue (off-specification).
  • D. No action required.

Answer: B

 

NEW QUESTION 28
Which of the following is not part of the composition of a Plan?

  • A. Product descriptions
  • B. Pre-requites
  • C. Assumptions
  • D. Quality responsibilities

Answer: D

Explanation:
Explanation/Reference:
Risk Theme
Testlet 1
Additional Information
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.

 

NEW QUESTION 29
PLANS
During the initiation stage, the project manager is creating the project plan.
Here are three activities carried out as part of PRINCE2's recommended approach to planning.
As part of which step of the approach (A-F) should each activity be carried out?
Choose only one step for each activity. Each step can be used once, more than once, or not at all.

Answer:

Explanation:
Explanation

 

NEW QUESTION 30
......


For more info read reference:

PRINCE2-Practitioner Exam Source

 

Pass PRINCE2 PRINCE2-Practitioner Exam Info and Free Practice Test: https://www.prepawayete.com/PRINCE2/PRINCE2-Practitioner-practice-exam-dumps.html

New 2023 Latest Questions PRINCE2-Practitioner Dumps - Use Updated PRINCE2 Exam: https://drive.google.com/open?id=1xtb3n6Q0hViKp5LWXZ_ez28MB2OiiNpL

Contact Us

If you have any question please leave me your email address, we will reply and send email to you in 12 hours.

Our Working Time: ( GMT 0:00-15:00 )
From Monday to Saturday

Support: Contact now